Guide
How long does it take to tile a bathroom?
A tiler takes three to four days to tile the walls and floor of a typical bathroom in Checkatrade's 2026 guide, and about four in MyJobQuote's. Stripping out, boarding, tanking and the waits before grouting and first use come on top, so the room is out of action for longer than the tiler is on site.
Updated
The short answer
Checkatrade's tiling cost guide (June 2026) gives three to four days to tile the walls and floor of a typical bathroom, and MyJobQuote's bathroom guide about four. Both are days of tiling for one tiler. Neither covers stripping out the old bathroom, the plumbing, or the waits the products need between stages, which is why a bathroom can be unusable for longer than the tiler is actually there.
Days by job size
| Job | Area | Tiling days |
|---|---|---|
| Small bathroom floor only | 5 m² of floor | Half a day |
| Shower enclosure walls | 8 m² of wall | 1 day |
| Half-tiled bathroom | 12 m² of wall, 5 m² of floor | 1.5 days |
| Bath and shower walls plus floor | 20 m² of wall, 5 m² of floor | 2.5 days |
| Fully tiled bathroom | 30 m² of wall, 6 m² of floor | 3.5 days |
| Fully tiled, old tiles off first | As above, with 25 m² of old tiles | 4.5 days |
These are worked out the way this site's tiling job card estimates days: Checkatrade's middle rates of 12 m² of wall and 10 m² of floor a day, half a day added for each 10 m² of old tile to strip, and the total rounded up to the next half day. A herringbone or mosaic floor takes longer again. They are working days on site, not the calendar.
What adds days around the tiling
- Stripping out. Old tiles, suite and boxing come out and the walls are made good, often a day on its own, more if plaster comes away with the tiles. See how to remove tiles.
- Plumbing. The bath or tray is fitted, levelled and tested before the walls are tiled down onto it.
- Boarding and levelling. Covering a timber floor with ply or backer board or levelling a screed, plus drying time for any compound.
- Tanking. The waterproof layer round the shower cures for its maker's stated time before tiling.
- Adhesive set. Standard adhesive is left about 24 hours before grouting, so grouting is often a separate visit.
- Silicone. The last joints go in after grouting and must cure before the shower is used.
How the week usually runs
For a bathroom with a shower over the bath, tiled walls round the wet areas and a tiled floor, the order on site usually goes: strip out and make good; the bath and pipes go in; tanking is applied and left to cure; the walls are set out and tiled; the floor is tiled last so nobody walks on it while the walls are done; grouting follows the next day, and silicone after that. With each trade booked straight after the last, a job with three days of tiling in it can still fill most of a working week, and any trade running late pushes the rest back.
Showers and wet rooms
A shower enclosure is the smallest area in the room but the most cutting per m²: a valve, a niche, the tray edge and two internal corners. A walk-in shower or wet room adds a floor laid to a slight slope (a fall) towards a drain, fully tanked, with its own cure before tiling, and small mosaic on that floor is slower again. After the last tile, allow for the waits before the first shower, set out in the guide to tile drying times.
Why your tiler's estimate may differ
Tile size cuts both ways: large format tiles cover area quickly but need flatter walls and two people to handle, while small tiles mean more joints and more cuts. An older house with walls out of plumb and corners out of square needs more setting out. Patterns take longer, as the guide to how many m² a tiler lays a day explains. A tiler who has seen the room will give a better figure than any table, so ask whether their days include stripping, boarding, grouting and silicone, and which days you cannot use the room.
Time and cost
Because many tilers price by the day, time and cost move together. The cost guides we use put tiling the walls and floor of a typical bathroom at £800 to £2,050 and a tiler's day at £150 to £350; the bathroom tiling cost page has the detail, and bathroom tiling covers what the job includes. For walls alone, see wall tiling costs.
Common questions
How long does it take to tile a bathroom floor?
A small bathroom floor of about 5 m² is roughly half a day's tiling on a prepared base, plus a return visit to grout. Lifting old tiles, boarding over timber or levelling adds to it.
How long does it take to tile a shower?
About a day of tiling for the walls of a typical enclosure, then grouting and silicone. The tanking must cure before tiling starts, and the shower stays unused until the grout and silicone have cured.
Can a bathroom be tiled in a day?
A small floor or a single wall can be fixed in a day, but grouting usually waits until the next day unless rapid-set adhesive is used. A full bathroom cannot.
Why is my tiling job taking longer than quoted?
Usually because the walls or floor needed more preparation once the old tiles were off, because tanking or plaster had to dry, or because another trade ran late. Ask for a revised plan when it happens.